Under construction5 of 11 complete
Antalya in Jogeshwari – Oshiwara is under construction: 5 of 11 buildings complete, with work progressing on the rest.
- Total area
- 17,62,939 sq ft
- Buildings / wings
- 11
- Tallest
- G + 40
- Mix
- Rehab and sale buildings
- Location
- Jogeshwari – OshiwaraWestern Suburbs
5 completed6 under construction0 future
Buildings & status
Status as of October 2026.
| Building / wing | Configuration | Area (sq ft) | Stage | Current status |
|---|---|---|---|---|
| Palantium – Rehab 1 | G + 8 | 70,252 | Completed | OC received |
| Palantium – Rehab 2 | G + 8 | 70,252 | Completed | OC received |
| SilverAvenue – Rehab 3A | G + 15 | 1,24,827 | Completed | OC received |
| SilverAvenue – Rehab 3B | G + 17 | 1,12,678 | Under construction | RCC Part 1 – 5th slab in progress; Part 2 – 3rd slab in progress |
| SilverAvenue – Rehab 3C & D | G + 16 | 1,55,008 | Under construction | RCC completed, finishing in progress |
| SilverAvenue – Sale 1 | G + P3 + 35 | 4,62,786 | Completed | OC received, handover in progress |
| SilverAvenue – Sale 1 Parking Tower | G + 19 | 30,000 | Under construction | RCC completed, mechanical completed |
| SilverAvenue – Sale 2 | G + 40 | 5,92,395 | Under construction | 20th slab in progress |
| SilverAvenue – R Mall | LG + G + upper floors | 65,625 | Under construction | RCC completed, finishing in progress |
| SilverAvenue – Rehab 4C | G + 11 | 65,206 | Under construction | RCC completed, finishing in progress |
| SilverAvenue – Rehab 7 | G + 7 | 13,910 | Completed | CFO received, OC received |